Bid for Hennepin Ave Water Main Construction Project (RCA-2020-00405)

ORIGINATING DEPARTMENT
Finance & Property Services and Public Works
To Committee(s)
# Committee Name Meeting Date
1 Policy & Government Oversight Committee Apr 22, 2020
Lead Staff:
Pam Fernandez
Presented By:
Robert Ervin
Action Item(s)
# File Type Subcategory Item Description
1 Action Bid

Accepting the low bid of Thomas and Sons Construction, Inc., submitted on Event No. 991, in the amount of $315,740.30, to provide all materials, labor, equipment, and incidentals necessary for the Hennepin Ave Water Main Construction Project, and authorizing a contract for the project, all in accordance with City specifications.

Previous Actions

None

Ward / Neighborhood / Address
# Ward Neighborhood Address
1. Not Applicable
Background Analysis

Tabulation of Four (4) bids submitted on Event 991 for Hennepin Water. Accepting the low bid of Thomas and Sons in the amount of $315,740.00 to provide all materials, labor, equipment and incidentals necessary for the Hennepin Avenue Water Main Construction Project, and authorizing a contract for the project, all in accordance with City specifications.

The water main in Hennepin Avenue between Washington Avenue and 3rd Street South is undersized. This project will replace the existing water main with a new, appropriately sized, water main. This work is being done prior to the Hennepin Avenue Paving project and is a standalone Water Capital project. As such, the funding for this project is from the Water Distribution Capital funding source WTR12.

Enterprise Review
  • Meets the City’s Equity and Inclusion goals for contracts over $100,000. Affirmative Action Plan approved by Civil Rights
  • Meets Small and Underutilized Business Program goals. SUBP goals: 0%