Contract amendment with MA Mortenson Company for additional carpentry and casework for the Public Service Building Project (RCA-2021-00945)
ORIGINATING DEPARTMENT
To Committee(s)
| # | Committee Name | Meeting Date |
|---|---|---|
| 1 | Policy & Government Oversight Committee | August 18, 2021 |
Action Item(s)
| # | File Type | Subcategory | Item Description |
|---|---|---|---|
| 1 | Action | Contract/Agreement | Authorizing an increase to Contract No. COM0001069 with MA Mortenson Company, in the amount of $67,319 for a total amount not to exceed $6,756,531, for increased carpentry and casework installation for the Public Service Building Project. |
Ward / Neighborhood / Address
| # | Ward | Neighborhood | Address |
|---|---|---|---|
| 1. | Ward 7 | Elliot Park | 505 4th Avenue South |
Background Analysis
The amendment is for four (4) increased scopes of work. The first increase, in the amount of $65,077 is for additional window shades on the East side of levels 3 and 4. The second increase in the amount of $1,385 is for an additional mail slot in the Property and Evidence lockers. The third increase, in the amount of $171 is for door hardware change for room 130 to add a card reader. The fourth increase, in the amount of $686 is for installing additional door hardware for egress and functionality revisions.